MoDOT: Interchange Project at Route 60/Route 125 in Rogersville
Beginning the Week of March 13
Rogersville, Greene County – Drivers can expect lane and median crossover closures, narrow lanes and traffic shifts on U.S. Route 60 and lane and road closures on Missouri Route 125 in Rogersville when contractor crews build a new interchange at U.S. Route 60/Route 125 intersection beginning the week of March 13, the Missouri Department of Transportation said.
Here’s a look at the project:
Build interchange at U.S. Route 60/Route 125 intersection
Build interchange ramps for safe access between U.S. Route 60 and Route 125
Build outer road from Missouri Route 125 to Farm Road 229 and Farm Road 243
Traffic Impacts:
All Stages
Narrowed lanes and traffic shifts on Route 60
Crews and equipment close to traffic in areas
Signs and message boards will alert drivers approaching the work zone
Drivers should look for alternate route
Stage 1 (March 13 – August 2023)
Farm Road 229 median crossover CLOSED permanently
Stage 2 (July – September 2023)
Expect significant traffic delays at the Route 60/Route 125 signal
Drivers are encouraged to look for alternate routes
Stage 3 (September 2023 – May 2024)
Expect significant traffic delays at the Route 60/Route 125 signal
Drivers are encouraged to look for alternate routes
Stage 4 (April – May 2024)
Route 60 left turn lanes onto Route 125 CLOSED
Route 125 traffic will not be allowed to turn left onto Route 60
Route 125 traffic will be allowed to turn right onto Route 60
Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
Signed detour used during this stage
Stage 5 (May – November 2024)
Route 125 CLOSED at Route 60
Route 60 will have no access to Route 125
Route 125 will have no access to Route 60
Route 60 median crossovers CLOSED between Route NN/J and Farm Road 247
Signed detour used during this stage
Weather and/or construction delays will alter the work schedule.
Project information:
Contractor: Capital Paving & Construction LLC, Jefferson City